Facebook
Home About us Projects Services Contact us
 
Pranav Constructions undertakes construction of small and medium size Premium/Deluxe apartments on their own plots
  Read more
Pranav Constructions is willing to associate with landowners to maximize the return on their property
  Read more
OCT 2012
Launch of Casa Essenza, Chennai
  Read more
At present we are offering an exceptional living space in Urapakkam, Thiruverkadu & Thoraipakkam which are located at Chennai District. We are privileged to offer these projects for our customers at the most competitive rates..
 
As we have thoroughly understood your preferences regarding a house, we plan and execute unique living space that matches your specifications.
 
 
 
WELCOME TO PRANAV CONSTRUCTIONS
We, Pranav Constructions, are a Flat Promoter & Builder ventured as a registered contractor in Chennai. Pranav Constructions was established in the year 2012 by Mr. Balasundaran, Engineering Graduate, who is having a Technical Expertise, Business Knowledge & clean Business Etiquettes. He has more than two Decades of Experience to his record and has held various top level positions in companies in India and Middle East.
  Read more

05/02/2014:"CASA ESSENZA"READY TO OCCUPY – ONLY TWO FLATS (2BHK – 650 sq. ft. and 3BHK – 1190 sq. ft.) ARE AVAILABLE.

05/02/2014:"PRATEEKSHA" – READY TO OCCUPY – ONLY TWO FLATS (2BHK - 730 & 820 sq. ft.) ARE AVAILABLE.

17.07.2013:“CASA FORTUNA”  –   Launching a new Apartment Project  at VPG Avenue Extension, Okkiam Thoraipakam, Behind AKDR Golf Village,Chennai – 600097.

28/10/2013:“CASA FORTUNA”-   PILE FOUNDATION COMPLETED
30/10/2013:“CASA FORTUNA”     - INSTALLATION OF BORE WELL WORK COMPLETED
04/11/2013:“CASA FORTUNA”     -PILE CAPPING WORK STARTED
13/11/2013:“CASA FORTUNA”    - PILE CAPPING WORK COMPLETED
15/11/2014:“CASA FORTUNA”    -  PLINTH BEAM WORK STARTED
.20/11/2014: “CASA FORTUNA”  -PLINTH BEAM CONCRETING COMPLETED
24/12/2014: “CASA FORTUNA”    -      SUMP TANK & SEWAGE TANK STARTED
03/12/2013:“CASA FORTUNA”    -COMPLETED SUMP TANK & SEWAGE TANK CONSTRUCTION
20.01.2014:“CASA FORTUNA”     - PCC WORK COMPLETED ON GROUND FLOOR
30.01.2014:“CASA FORTUNA”     - COLUMNS RAISED FROM GROUND FLOOR TO FIRST ROOF
31.01.2014:“CASA FORTUNA”     - BRICK WORK STARTED FOR STAIRCASE AREA TO ENABLE TO START FIRST FLOOR ROOF CONCRETING.
07.02.2014:“CASA FORTUNA”      - SHUTTERING WORK STARTED FOR 1ST ROOF SLAB CONCRETING
19.02.2014:“CASA FORTUNA”      -SUCESSFULLY COMPLETED 1ST ROOF (GROUND FLOOR ROOF) SLAB with RMC CONCRETING
26.02.2014:“CASA FORTUNA”     -ALL COLUMNS RAISED FOR 2ND ROOF SLAB
03.03.2014:“CASA FORTUNA”    - SHUTTERING WORK STARTED FOR 2ND ROOF SLAB
08.03.2014:“CASA FORTUNA”     - BRICK WORK AT GROUND FLOOR STARTED
13.03.2014: “CASA FORTUNA”    - SUCESSFULLY COMPLETED 2ND ROOF (FIRST FLOOR ROOF) SLAB with RMC CONCRETING.
23.03.2014:“CASA FORTUNA”     -COMPLETED GROUND FLOOR BRICK WORKS & LOFTs IN KITCHEN & BED ROOMS.
27.03.2014:“CASA FORTUNA”     -  STARTED BRICK WORK AT GROUND FLOOR STARTED
28.03.2014:“CASA FORTUNA”   -SUCESSFULLY COMPLETED 3RD ROOF (2ND FLOOR ROOF) SLAB with RMC CONCRETING.
27.03.2014:“CASA FORTUNA”-STARTED BRICK WORK AT FIRST FLOOR
05.04.2014:“CASA FORTUNA” -   POOJA PERFORMED FOR FIXING OF 1ST MAIN DOOR FRAME (VASAKAAL POOJA).
10.04.2014:“CASA FORTUNA”-STARTED LAYING OF ELECTRICAL CONDUITE PIPES AND JUNCTION BOXES AT GROUND FLOOR
12.04.2014:“CASA FORTUNA”-SECOND FLOOR BRICK WORK STARTED.
13.04.2014:“CASA FORTUNA”-COMPLETED FIXING OF DOOR FRAMES AND WINDOW FRAMES IN GRUND FLOOR FLATS.
15.04.2014:“CASA FORTUNA”-COMPLETED ELELCTRICAL WORKS OF CONSEALED CONDUIT PIPES, JUNCTIONS BOXES, FLATS’ MAIN DB BOXES FROM GROUND FLOOR FLATS.
15.04.2014:“CASA FORTUNA”-FIRST FLOOR BRICK WORK COMPLETED
18.04.2014:“CASA FORTUNA”-INNER PLASTERING WORK STARTED IN GROUND FLOOR FLATS
19.04.2014:“CASA FORTUNA”-    STARTED ELELCTRICAL WORKS OF CONSEALED CONDUIT PIPES, JUNCTIONS BOXES, FLATS’ MAIN DB BOXES FROM FIRST & SECOND FLOOR FLATS.
22.04.2014: “CASA FORTUNA”-COMPLETED SECOND FLOOR FLATS BRICK WORK
25.04.2014: “CASA FORTUNA”  -  Completed Inner Plastering works at Ground Floor
26.04.2014: “CASA FORTUNA” -   Started Inner Plastering works at First Floor Flats
02.05.2014:  “CASA FORTUNA”-   Plumbing Work Started in Ground Floor Flats
02.05.2014:“CASA FORTUNA”-    Started Painting ‘PUTTY’ Work in Ground Floor Flats
06.05.2014:“CASA FORTUNA” -    Completed Inner Plastering Works at First Floor Flats
06.05.2014:“CASA FORTUNA” -    Completed Painting ‘PUTTY’ work in Ground Floor Flats and Started in Second Floor
06.05.2014:“CASA FORTUNA”-     Completed Electrical Concealed Piping works in All Floors/Flats.
.07.05.2014:“CASA FORTUNA” -   Started Inner Plastering works at Second Floor Flat.
13.05.2014: “CASA FORTUNA”-STARTED CONSTRUCTING WOODEN SCAFFOLDING FOR OUTER PLASTERING
14.05.2014:“CASA FORTUNA” -    COMPLETED ALL INNER PLASTERING WORKS INCLUDING STAIR CASE AREAS
14.05.2014:“CASA FORTUNA”- STARTED CONSTRUCTING ‘OVER HEAD WATER TANK’
15.05.2014:“CASA FORTUNA”-STARTED OUTER PLASTERING WORKS
15.05.2014: “CASA FORTUNA”-STARTED ELECTRICAL CABLE/WIRE PULLING IN ALL FLATS
15.05.2014: “CASA FORTUNA”-STARTED CARPENTRY WORK FOR MAKING WINDOWS SHUTTERING
15.05.2014:“CASA FORTUNA”-PAINTING ‘PUTTY’ WORK UNDER PROGRESS IN ALL FLATS
22.05.2014:“CASA FORTUNA”-COMPLETED 2 SIDES OF OUTER PLASTERING WORKS.
23.05.2014:“CASA FORTUNA”  - STARTED WOODEN SCAFFOLDING FOR 3RD SIDE (WEST SIDE) OF THE BUILDING FOR OUTSIDE PLASTRING.
24.05.2014:“CASA FORTUNA”  -COMPLETED ALL 10 TOILETS INSIDE PLUMBING CONCEALED PIPING WORKS.
24.05.2014:“CASA FORTUNA”  - STARTED WOODEN SCAFFOLDING FOR FRONT SIDE OF THE BUILDING
25.05.2014:“CASA FORTUNA”  - COMPLETED ALL ELECTRICAL WIRE PULLING WORK IN THE BUILDING
27.05.2014:“CASA FORTUNA” - COMPLETED WEST SIDE (3RD SIDE) OUTER PLASTERING WORKS
28.05.2014:“CASA FORTUNA” - COMPLETED OVERHEAD WATER TANK INCLUDING LEAK PROOFING AND PLASTERING.
28.05.2014:“CASA FORTUNA”  - STARTED FRONT SIDE OUTER PLASTERING WORK and STARTED COMPOUND WALL PLASTERING WORKS.
29.05.2014:“CASA FORTUNA”  - COMPOUND WALL CONSTRUCTION COMPLETED @ BOTH SIDE.
30.05.2014:“CASA FORTUNA”  - STARTED KITCHEN PLATFOR GRANITE LAYING WORKS and CUDAPPA SLABS FOR BED ROOM WARDROBES AND ALL KITCHEN SHELF.
30.05.2014:“CASA FORTUNA” - STARTED FIXING TEAK WOODEN FRAMES FOR WINDOWS.
31.05.2014:“CASA FORTUNA”  -  BLACK GRANITE SLABS LAYED IN ALL KITCHENS
02.06.2014:“CASA FORTUNA”  - COMPLETED OUTSIDE BUILDING PLASTERING WORKS.
03.06.2014:“CASA FORTUNA” - STARTED LAYING WALL & FLOOR TILES IN ALL BATHROOMS.
04.06.2014:“CASA FORTUNA” - STARTED OUTSIDE PLUMBING WORKS.
07.06.2014:“CASA FORTUNA” - FIXED TEAK WOOD MAIN DOORS FOR ALL FLATS.
10.06.2014:“CASA FORTUNA” - COMPLETED LAYING WAL & FLOOR TILES IN ALL BATHROOMS.
10.06.2014:“CASA FORTUNA” - STARTED OUTSIDE PUTTY WORK FOR PAINTING.
14.06.2014: “CASA FORTUNA”-  1st COAT PAINTING COMPLETED FOR OUTSIDE BUILDING.
15.06.2014: “CASA FORTUNA”    - WEATHERING COURSE AT TERRACE COMPLETED
19.06.2014: “CASA FORTUNA”-    STARTED LAYING OF TILES ON WEATHERING COURSE.
21.06.2014: “CASA FORTUNA”    -COMPLETED LAYING OF TILES ON WEATHERING COURSE.
27.06.2014:“CASA FORTUNA”-STAIRCASE HANDRAIL (STEEL) WORK COMPLETED.
29.06.2014:“CASA FORTUNA”- COMPLETED FIXING OF FABRICATED MAIN GATES AT MAIN ENTRANCE.
01.07.2014:“CASA FORTUNA”- STARTED FLOORING OF CAR PARKING & COMMON AREAS
02.07.2014:“CASA FORTUNA”- COMPLETED FLOORING OF CAR PARKING & COMMON AREAS.
03.07.2014:“CASA FORTUNA”- STARTED FIXING OF PVC DOORS & ALUMINIUM WINDOWS FOR VENTILLATION IN ALL BATHROOMS.
04.07.2014:“CASA FORTUNA”- COMPLETED FIXING OF PVC DOORS & ALUMINIUM WINDOWS FOR VENTILLATION IN ALL BATHROOMS.
05.07.2014:“CASA FORTUNA”- COMPLETED CIVIL WORKS FOR RAMP IN FRONT OF THE BUILDING FOR CAR PARKING.
08.07.2014:“CASA FORTUNA”- STARTED 1ST COAT OF PAINTING INSIDE FLATS.
09.07.2014:“CASA FORTUNA”- APPLIED 3PHASE EB SERVICE CONNECTION FOR ALL 6 FLATS.
10.07.2014:“CASA FORTUNA”- COMPLETED FLOOR TAIL LAYING WORKS IN ALL SIX FLATS.
12.07.2014:“CASA FORTUNA"-    COMPLETED THE WORK OF  ‘RAIN HARVEST SYSTEM’ IN THE BUILDING.
15.07.2014: “CASA FORTUNA"-   COMPLETED LAYING TILES IN STAIRCASE AND COMMON AREAS.
16.07.2014:“CASA FORTUNA"-    FIXED SAFETY GATE FOR TERRANCE ENTRANCE AND SAFETY GRILLS FOR OTS IN TERRACE.
19.07.2014:“CASA FORTUNA"-STARTED FIXING OF SWITCHES, DB SWITCHES, MCB, HOLDER, FAN REGULATORS AND OTHER FINAL ELECTRICAL WORKS IN THE BUILDING.
25.07.2014:“CASA FORTUNA"-STARTED FIXING OF TOILET FITTINGS LIKE, SHOWER, MIXER, WATER TAPS, EWC, WASH BASIN Etc. IN THE BUILDING.
25.07.2014:“CASA FORTUNA"- COMPLETED FINAL PAINTING INSIDE TWO GROUND FLOOR FLATS IN THE  BUILDING.